Contract No: HK/2011/07

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 2)

 

Environmental Permit no. EP-364/2009/A,

Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a and FEP-07/364/2009/A

 

Monthly Environmental Monitoring & Audit Report

 

- may 2012 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                        

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

7 June 2012


Table of contents     

 

EXECUTIVE SUMMARY. 4

1.   Introduction. 8

1.1    Scope of the Report 8

1.2    Structure of the Report 8

2.   Project Background. 9

2.1    Background. 9

2.2    Scope of the Project and Site Description. 9

2.3    Division of the Project Responsibility. 10

2.4    Project Organization and Contact Personnel 10

3.   status of regulatory compliance. 15

3.1    Status of Environmental Licensing and Permitting under the Project 15

4.   Monitoring Requirements. 23

4.1    Noise Monitoring. 23

4.2    Air Monitoring. 24

5.   Monitoring Results. 27

5.1    Noise Monitoring Results. 27

5.2    Real Time Noise Monitoring Results. 29

5.3    Air Monitoring Results. 30

5.4    Waste Monitoring Results. 32

6.   Compliance Audit. 35

6.1    Noise Monitoring. 35

6.2    Real Time Noise Monitoring. 35

6.3    Air Monitoring. 35

6.4    Review of the Reasons for and the Implications of Non-compliance. 36

6.5    Summary of action taken in the event of and follow-up on non-compliance. 36

7.   Cumulative Construction Impact due to the Concurrent Projects. 36

8.   Environmental Site Audit. 38

9.   Complaints, Notification of Summons and Prosecution. 47

10.  Conclusion. 43


lIST OF TABLES

 

Table 2.1    Schedule 2 Designated Projects under this Project

Table 2.2   Details of Individual Contracts under the Project

Table 2.3   Contact Details of Key Personnel

Table 3.1   Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2   Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/17

Table 3.3   Summary of submission status under FEP-03/364/2009

Table 3.4   Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.5   Summary of submission status under FEP-02/364/2009

Table 3.6   Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.7   Summary of submission status under FEP-01/364/2009

Table 3.8   Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Table 3.9   Summary of submission status under FEP-05/364/2009/A

Table 3.10  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.11  Summary of submission status under FEP-06/364/2009/A

Table 3.12  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Table 3.13  Summary of submission status under FEP-07/364/2009/A

Table 4.1   Noise Monitoring Stations

Table 4.2   Real Time Noise Monitoring Stations

Table 4.3   Air Monitoring Stations

Table 5.1    Noise Monitoring Stations for Contract no. HY/2009/17

Table 5.2    Noise Monitoring Stations for Contract no. HY/2009/18

Table 5.3    Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Table 5.4    Noise Monitoring Stations for Contract no. HY/2009/15

Table 5.5    Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.6   Real Time Noise Monitoring Stations for Contract no. HY/2009/17

Table 5.7   Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Table 5.8    Air Monitoring Station for Contract no. HY/2009/17

Table 5.9    Air Monitoring Stations for Contract no. HY/2009/18

Table 5.10   Air Monitoring Station for Contract no. HK/2009/01

Table 5.11   Air Monitoring Station for Contract no. HK/2009/02

Table 5.12   Air Monitoring Station for Contract no. HY/2009/15

Table 5.13   Air Monitoring Stations for Contract no. HY/2009/19

Table 5.14  Details of Waste Disposal for Contract no. HY/2009/17

Table 5.15  Details of Waste Disposal for Contract no. HK/2009/01

Table 5.16  Details of Waste Disposal for Contract no. HK/2009/02

Table 5.17  Details of Waste Disposal for Contract no. HY/2009/18

Table 5.18  Details of Waste Disposal for Contract no. HY/2009/15

Table 5.19  Details of Waste Disposal for Contract no. HY/2009/19

Table 8.1   Summary of Environmental Inspections for Contract no. HY/2009/15

Table 8.2   Summary of Environmental Inspections for Contract no. HY/2009/18

Table 8.3   Summary of Environmental Inspections for Contract no. HY/2009/19

Table 8.4   Summary of Environmental Inspections for Contract no. HK/2009/01

Table 8.5   Summary of Environmental Inspections for Contract no. HK/2009/02

Table 9.1   Cumulative Statistics on Complaints

Table 9.2   Cumulative Statistics on Successful Prosecutions

Table 10.1  Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

 


lIST OF FIGUREs

 

Figure 2.1       Project Layout

Figure 2.2       Project Organization Chart

Figure 4.1        Locations of Environmental Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix 3.1     Environmental Mitigation Implementation Schedule

Appendix 4.1     Action and Limit Level

Appendix 4.2     Copies of Calibration Certificates

Appendix 5.1     Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2     Noise Monitoring Results and Graphical Presentations

Appendix 5.3     Air Quality Monitoring Results and Graphical Presentations

Appendix 5.4     Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1     Event Action Plans

Appendix 6.2     Notification of Exceedance

Appendix 9.1     Complaint Log

Appendix 10.1   Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

         i.            This is the Environmental Monitoring and Audit (EM&A) Monthly Report  /span> May 2012 specific for Environmental Permit no. EP-364/2009/A, Further Environmental Permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-03-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2011/07  /span> Wan Chai Development Phase II and Central Wanchai Bypass  Sampling, Field Measurement and Testing Works (Stage 2). This report presents the environmental monitoring findings and information recorded during the period April to May 2012. The cut-off date of reporting is at 27th of each reporting month.

 

  1. Contract no. HY/2010/06, Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line, has submitted an application for Further Environmental Permit under EP-364/2009/A on 21 May 2012.

 

      iii.            In the reporting month, the principal work activities of individual contracts are included as follows:

 

Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009

 

 -           ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A

 -           Trial Pit

 -           Instrumentation and monitoring works

 -           Drainage works

 -           Site investigation and pre-drilling works

 -           D-wall construction

 -           Sheet piling

 -           Grout curtain

 -           Tree Transplantation

 -           Earthwork

 -           Preparation works in existing tunnel

 -           Stitch coring

 -           Approach ramp structure works

 -           Top down slab

 -           Road works

 -           Tunnel works

 -           Excavation and Lateral Support

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

 -           Diaphragm wall construction works for CWB (Stage2)

 -           Pre-drilling works for CWB (Stage 2)

 -           Pre-bored H piling works for SCL

 -           Construction of flowmeter chamber (FMC1) for cross harbour watermains (CHC) at north bank of HKCEC Water Channel

 -           Excavation for CWB top slab

 -           Shear pin installation work for SCL Diaphragm wall

 -            /span>Trimming of SCL Diaphragm wall head

 -           Installation of dewatering well, recharging well, observation well and associated system for construction of CWB tunnel, SCL top slab and Exhaust duct at Stage 1

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

 -           Breaking concrete slab and excavation of trial pit at tunnel portion 3 & 4

 -           Drilling bored pile to rock head at tunnel portion 3 & 4

 -           Deep excavation works were ongoing below -8.8 mPD for western tunnel portion 1 and below -5.8mPD for eastern tunnel portion

 -           Tunnel bored pile works at WCR4 area

 -           Trial Pit excavation of D-wall at Portion 3&4

 -           Pre-drilling of bored pile

 

Contract no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 -           Diaphragm wall construction works at TS4

 -           ELS works at TPCWAE

 -           Cut and Cover Tunnel Construction at TS1

 -           Night time protection works at CHT

 -           Cut off wall preparation works at Hung Hing Road and POC

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

 -           Road works at Watson Road

 -           Fabrication of bored piling platform

 -           Bored piling (Land)

 -           Ground contamination assessment

 -           Pre-drilling works for bored pile and Diaphragm wall

 -           D-wall Construction (North & South Section)

 -           Guide wall construction for D-wall / Barette at North side

 -           Construction works for Box Culvert T

 -           Marine Piling

 -           Construct ion of socket-H pile for Marine works

 -           Construction of pre-bored H-pile works for Culvert U

 

Noise Monitoring

Monitoring for report of review baseline noise level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20 June 2011, verified by IEC on 18 July 2011 and was approved by ER by January 2012. The new baseline is used for the noise calculation of this reporting month starting from January 2012.

      iv.            Due to adverse weather condition, the noise monitoring at the following stations were rescheduled

M7e: from 16 May 2012 to 18 May 2012

M7w: from 16 May 2012 to 18 May 2012

  1. Noise monitoring during daytime was conducted at M1a - Harbour Road Sports Center; M2b - Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b - City Garden, M6 - HK Baptist Church Henrietta Secondary School, M7e and M7w  International Finance Centre Eastern and Western End of Podium on a weekly basis.
  2. 1 limit level exceedance was recorded at M7e  International Finance Centre Eastern on 30 April 2012. After checking contractors work schedules and investigation found that construction works were conducted as the major noise sources contributed in the noise monitoring. The exceedance was considered as project related.
  3. 2 limit level exceedances were recorded at M6  HK Baptist Church Henrietta Secondary School on 30 April and 16 May 2012. After checking contractors work schedules and investigation found that traffic was the major noise sources contributed in the noise monitoring. The exceedances were considered as non-project related.

   viii.            24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitefield Depot for the pilling works in FEHD Whitfield Depot and RTN2  Tunnel (North Point Section) and Island Eastern Corridor Link. No project related action and limit level exceedance was recorded in the reporting period.

 

Air Monitoring

  1. Due to extension of site boundary by contractor of HY/2009/19, location of air monitoring station CMA1b  Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.

       x.            Due to lack of electricity supply, the 24-hr TSP monitoring at the following stations were rescheduled

CMA1b: from 8 May 2012 to 9 May 2012

CMA5a: from 8 and 25 May 2012 to 9 and 26 May 2012

MA1e: from 14 May 2012 to 15 May 2012

 

     xi.            1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b - Oil Street Community Liaison Centre; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a  Society for the Prevention of Cruelty to Animals; CMA5a - Children Garden opposite to Pedestrian Plaza; MA1e and MA1w  International Finance Centre eastern and western wing on every six days basis. No action and limit level exceedance were recorded in the reporting period.

 

Complaints, Notifications of Summons and Successful Prosecutions

    xii.            There was no environmental complaint received in this reporting month.

 

Site Inspections and Audit

  xiii.            The Environmental Team (ET) conducted weekly site inspections for Contract no. HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01 and HK/2009/02 in this reporting period. The Contractors rectified major observations and recommendations made during the audit sessions. No non-conformance was identified during the site inspections.

 

Future Key Issues

   xiv.            In the coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009

 

 -           ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

 

 -           Trial pit

 -           Instrumentation and monitoring works

 -           Drainage works

 -           Site investigation and pre-drilling works

 -           D-wall construction

 -           Sheet piling

 -           Grout curtain

 -           Tree Transplantation

 -           Earthworks

 -           Preparation works in existing tunnel

 -           Stitch coring

 -           Approach ramp structure works

 -           Top down slab

 -           Road works

 -           Tunnel works

 -           Excavation and Lateral Support

 

Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009

 -           Diaphragm wall construction for CWB tunneling works at Stage2

 -           Piling works for SCL Protection Works

 -           Installation of dewatering system for construction of CWB tunnel, SCL top slab and Exhaust duct at Stage 1

 -           Construction of CWB top slab would be continued

 -           Construction of SCL top slab and exhaust duct at Stage 1

 -           Pipe bridge erection upon completion of pipe laying works across exhaust duct, bulk excavation for construction of exhaust duct structure after installation of pipe bridge

 

Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

 -           Deep excavation works below -8.8mPD for western tunnel portion and below +5.8mPD for eastern tunnel portion.

 -           Drilling bored pile to rock head, breaking concrete slab and excavation of trial pit at tunnel portion 3 & 4.

 

Contract no. HY/2009/15   Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 -           Diaphragm wall construction works at TS4

 -           Cut and Cover Tunnel Construction at TPCWAE

 -           Night time protection works at CHT

 -           Cut off wall preparation works at Hung Hing Road and POC

 

Contract no. HY/2009/19  Central   Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

 -           Road works at Watson Road

 -           Fabrication of bored piling platform

 -           Bored piling (Land)

 -           Ground contamination assessment

 -           Pre-drilling works for bored pile and Diaphragm wall

 -           D-wall Construction (North & South Section)

 -           Guide wall construction for D-wall / Barette at North side

 -           Construction works for Box Culvert T

 -           Marine Piling

 -           Construct ion of socket-H pile for Marine works

 -           Construction of pre-bored H-pile works for Culvert U

 -           Construction of 1500 drainage along D-wall

 -           Construction of sheet pile at D9 location.

 

1     Introduction

1.1               Scope of the Report

1.1.1.        Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.        This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and  /span>Environmental Monitoring and Audit Requirements /span> under Particular Specification Section 27.

1.1.3.        This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-364/2009/A, Further Environmental Permit (FEP) nos. FEP-01-364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A during the period April to May 2012. The cut-off date of reporting is at 27th of each reporting month.

 

1.2               Structure of the Report

 

Section 1     Introduction  details the scope and structure of the report.

 

Section 2     Project Background  summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3     Status of Regulatory Compliance   summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4     Monitoring Requirements  summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5     Monitoring Results  summarizes the monitoring results obtained in the reporting period.

 

Section 6     Compliance Audit   summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7     Cumulative Construction Impact due to the Concurrent Projects  summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8     Site Inspection  summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9     Complaints, Notification of summons and Prosecution   summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10    Conclusion

2     Project Background

2.1               Background

2.1.1.        “Wan Chai Development phase II and Central-Wan Chai Bypass and “Central-Wan Chai Bypass and Island Eastern Corridor Link (hereafter called “the Project  are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.        The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.        There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2               Scope of the Project and Site Description

2.2.1.        Design and Construction of Central  Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.         The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

 -           A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

 -           The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

 -           Tunnel control buildings and ventilation buildings;

 -           Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

 -           Associated road lighting, road signing, traffic control and surveillance system; and

 -           Other associated works.

 

2.2.3.        The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (Eps) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1   Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3               Division of the Project Responsibility

2.3.1.        Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.        In the reporting month, Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) was commenced on 13 July 2011. The details of individual contracts are summarized in Table2.2.

Table 2.2  Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works.

DP1

5 October 2010

HY/2009/18

Central  Wan Chai Bypass (CWB)  Central Interchange

DP1

21 April 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010 (Completed)

HK/2009/01

Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai East(CWB Tunnel)

DP1

26 April 2011

HY/2009/15

Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section)

DP1

13 July 2011

HY/2009/19

Central  Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

 

2.4               Project Organization and Contact Personnel

2.4.1.        Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.        The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3  Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer’s Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer’s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3922 8332

3529 2829

Lam Woo & CO., LTD.

Contractor under Contract no. HY/2009/17

Project Manager

Mr. K. S. Law

9090 1378

2566 7522

Site Agent

Mr. Tony Au

 

9725 5874

2566 7522

Sub Agent

Mr. Johnny Wong

9725 5870

2566 7522

Chun Wo  Leader Joint Venture

Contractor under Contract no. HK/2009/01

Joint Venture Board Representative

Mr. PL Yue

2162 9909

2634 1626

Site Agent

Mr. Paul Yu

9456 9819

Sub Agent

Mr. Terry Wong

9757 9846

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Jack Chu

9775 2467

Construction Manager

Mr KK Yuen

9498 1213

Construction Manager

Mr. Andy Yu

9648 4896

Environmental Officer (Compliance Manager)

Mr. Andy Mak

9103 2370

Environmental Supervisor

Ms. Kiwi Chan

6227 8840

 

 

Environmental Supervisor

Mr. Yeung Sze King

9047 9952

 

Environmental Supervisor

Mr. Les Chow

6692 2423

 

Chun Wo  CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Site Agent

Mr. Chan Sing Cho

3658-3002

2827 9996

Quality & Environmental Manager

Mr. C.P. Ho

3658-3000

Environmental Officer

Ms Flora Ng

 

3658-3064

Chun Wo - CRGL - MBEC Joint Venture

 

Contractor under Contract no. HY/2009/19

Project Manager

Mr. Rayland Lee

3758 8879

2570 8013

Site Agent

Mr. Cheung Kit Cheung

6909 1555

Assistant Site Agent

Mr. Eric Fong

6191 9337

Environmental Engineer

Mr. Simon Wong

9281 4346

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Construction Manager (Marine)

William Luk

9610 1101

Construction Manager

(Land)

Patrick Cheung

9643 3012

Operation Manager (Land)

Yung Kwok Wah

9834 1010

Leighton Contractors (Asia) Limited

Contractor under Contract no. HY/2009/18

Site Agent

Mr. Brian Gillon

2214 7700

2140 6799

Deputy Site Agent

Mr. Desmond Sze

2214 7703

Environmental Officer

Mr. Anfernee Chow

2214 7721

Environmental Supervisor

K. P. Lai

6461 4660

Environmental Supervisor

Ray Cheng

2214 7742

Environmental Supervisor

K. W. Lee

6461 4623

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Chan Wai Hung

2823 7813

2865 5229

Site Manager

Mr. P.J. Fan

3557 6368

2566 2192

Contractor’s Representative

Mr. David Lau

3557 6358

Head of construction

Mr. Roger Cheung

3557 6371

Environmental Officer

Mr. Daniel Sin

3557 6215

Environmental Supervisor

Mr. Kelven Yip

3557 6347

Environmental Supervisor

Mr. Tim Fung

3557 6349

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3743 0788

3548 6988

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.4.3.        In this reporting month, the principal work activities of individual contracts are included as follows:

Contract no. HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009

 

 -           ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

 

 -           Trial Pit

 -           Instrumentation and monitoring works

 -           Drainage works

 -           Site investigation and pre-drilling works

 -           D-wall construction

 -           Sheet piling

 -           Grout curtain

 -           Tree Transplantation

 -           Earthwork

 -           Preparation works in existing tunnel

 -           Stitch coring

 -           Approach ramp structure works

 -           Top down slab

 -           Road works

 -           Tunnel works

 -           Excavation and Lateral Support

 

Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009

 -           Diaphragm wall construction works for CWB (Stage2)

 -           Pre-drilling works for CWB (Stage 2)

 -           Pre-bored H piling works for SCL

 -           Construction of flowmeter chamber (FMC1) for cross harbour watermains (CHC) at north bank of HKCEC Water Channel

 -           Excavation for CWB top slab

 -           Shear pin installation work for SCL Diaphragm wall

 -           Trimming of SCL Diaphragm wall head

 -           Installation of dewatering well, recharging well, observation well and associated system for construction of CWB tunnel, SCL top slab and Exhaust duct at Stage 1

 

Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

 -           Breaking concrete slab and excavation of trial pit at tunnel portion 3 & 4

 -           Drilling bored pile to rock head at tunnel portion 3 & 4

 -           Deep excavation works were ongoing below -8.8 mPD for western tunnel portion 1 and below -5.8mPD for eastern tunnel portion

 -           Tunnel bored pile works at WCR4 area

 -           Trial Pit excavation of D-wall at Portion 3&4

 -           Pre-drilling of bored pile

 

Contract no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 -           Diaphragm wall construction works at TS4

 -           ELS works at TPCWAE

 -           Cut and Cover Tunnel Construction at TS1

 -           Night time protection works at CHT

 -           Cut off wall preparation works at Hung Hing Road and POC

 

Contract no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

 -           Road works at Watson Road

 -           Fabrication of bored piling platform

 -           Bored piling (Land)

 -           Ground contamination assessment

 -           Pre-drilling works for bored pile and Diaphragm wall

 -           D-wall Construction (North & South Section)

 -           Guide wall construction for D-wall / Barette at North side

 -           Construction works for Box Culvert T

 -           Marine Piling

 -           Construct ion of socket-H pile for Marine works

 -           Construction of pre-bored H-pile works for Culvert U

2.4.4.        In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

Contract no. HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009

 -           ELS works for basement construction for pile cap construction.

 

Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

 -           Trial pit

 -           Instrumentation and monitoring works

 -           Drainage works

 -           Site investigation and pre-drilling works

 -           D-wall construction

 -           Sheet piling

 -           Grout curtain

 -           Tree Transplantation

 -           Earthworks

 -           Preparation works in existing tunnel

 -           Stitch coring

 -           Approach ramp structure works

 -           Top down slab

 -           Road works

 -           Tunnel works

 -           Excavation and Lateral Support

 

Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009

 -           Diaphragm wall construction for CWB tunneling works at Stage2

 -           Piling works for SCL Protection Works

 -           Installation of dewatering system for construction of CWB tunnel, SCL top slab and Exhaust duct at Stage 1

 -           Construction of CWB top slab would be continued

 -           Construction of SCL top slab and exhaust duct at Stage 1

 -           Pipe bridge erection upon completion of pipe laying works across exhaust duct, bulk excavation for construction of exhaust duct structure after installation of pipe bridge

 

Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

 -           Deep excavation works below -8.8mPD for western tunnel portion and below +5.8mPD for eastern tunnel portion.

 -           Drilling bored pile to rock head, breaking concrete slab and excavation of trial pit at tunnel portion 3 & 4.

 

Contract no. HY/2009/15   Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

 -           Diaphragm wall construction works at TS4

 -           Cut and Cover Tunnel Construction at TPCWAE

 -           Night time protection works at CHT

 -           Cut off wall preparation works at Hung Hing Road and POC

 

Contract no. HY/2009/19  Central   Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

 -           Road works at Watson Road

 -           Fabrication of bored piling platform

 -           Bored piling (Land)

 -           Ground contamination assessment

 -           Pre-drilling works for bored pile and Diaphragm wall

 -           D-wall Construction (North & South Section)

 -           Guide wall construction for D-wall / Barette at North side

 -           Construction works for Box Culvert T

 -           Marine Piling

 -           Construct ion of socket-H pile for Marine works

 -           Construction of pre-bored H-pile works for Culvert U

 -           Construction of 1500 drainage along D-wall

 -           Construction of sheet pile at D9 location.

 

 

3     status of regulatory compliance

3.1               Status of Environmental Licensing and Permitting under the Project

 

3.1.1.        A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1  Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-364/2009/A

 4 Aug 2010

Valid

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Valid

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

15 Nov 2010

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 July 2010

Valid

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Surrendered

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Valid

 

3.1.2.        Contract no. HY/2010/06, Wan Chai Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line, has submitted an application for Further Environmental Permit under EP-364/2009/A on 21 May 2012.

3.1.3.        Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009

3.1.4.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-03/364/2009 for contract no. HY/2009/17 showed in Table 3.2 and Table 3.3.

 

Table 3.2  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/17

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/364/2009

12 Jul 2010

N/A

Valid

Notification of Works Under APCO

319348

13 Jul 2010

N/A

Valid

Discharge Licence

WT00007212-2010

5 Aug 2010

5 Aug 2010  31 Aug 2015

Valid

Registration as a Waste Producer

5213-151-L2608-05

13 July 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7010400

16 Mar 2010

N/A

Valid

 

Table 3.3  Summary of submission status under FEP-03/364/2009

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

18 September 2010

Conditions 2.7 and 2.8

Submission of works schedule and location plan

1 September 2010

Condition 2.9

Noise Management Plan

1 September 2010

 

Contract no. 04/HY/2006  /span> Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A

3.1.5.        The construction works was completed, and the FEP was surrendered by the Contractor on 11 February 2011.

Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009

3.1.6.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.4 and Table 3.5

Table 3.4  Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088

6 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS1031-11

02 Nov 2011

07 Nov 2011 to 05 May 2012

Expired on 5 May 12

 

GW-RS1094-11

23 Nov 2011

27 Nov 2011 to 26 May 2012

Expired on 26 May 12

 

GW-RS1221-11

30 Dec 2011

20 Jan 2012 to 19 Jul 2012

Valid

 

GW-RS1227-11

30 Dec 2011

30 Dec 2011 to 26 Jul 2012

Cancelled

 

GW-RS0038-12

16 Jan 2012

15 Jan 2012 to 12 Jul 2012

Cancelled

 

GW-RS0158-12

24 Feb 2012

24 Feb 2012 to 23 Aug 2012

Valid

 

GW-RS0181-12

24 Feb 2012

27 Feb 2012 to 23 Aug 2012

Valid

 

GW-RS0213-12

28 Feb 2012

29 Feb 2012 to 27 Aug 2012

Valid

 

GW-RS0225-12

02 Mar 2012

14 Mar 2011 to 13 Sep 2012

Valid

 

GW-RS0227-12

02 Mar 2012

16 Mar 2011 to 15 Sep 2012

Valid

 

GW-RE0174-12

05 Mar 2012

30 Mar 2012 to  /span>29 Sep 2012

Valid

 

GW-RS0312-12

28 Mar 2012

30 Mar 2012 to  /span>29 Sep 2012

Valid

 

GW-RS0314-12

29 Mar 2012

30 Mar 2012 to 25 Sep 2012

Cancelled

 

GW-RS0356-12

03 Apr 2012

11 Apr 2012  to 29 Sep 2012

Valid

 

GW-RS0394-12

16 Apr 2012

19 Apr 2012  to 12 Oct 2012

Valid

 

GW-RS0459-12

3 May 2012

7 May 2012 to  /span>6 Nov 2012

Valid

 

GW-RS0460-12

10 May 2012

13 May 2012 to 6 Nov 2012

Valid

 

GW-RS0492-12

14 May 2012

15 May 2012 to 3 June 2012

Valid

 

GW-RS0514-12

14 May 2012

27 May 2012 to 26 Nov 2012

Valid

Discharge Licence

WT00006220-2010

18 Mar 2010

31 Mar 2015

Valid

 

WT00009641-2011

24 Jul 2011

31 Jul 2016

Valid

Billing account under Waste Disposal Ordinance

7010069

21 Jan 2010

N/A

Valid

Registration as a Chemical Waste Producer

WPN5213-134-C3585-01

21 Jan 2010

N/A

Valid

 

Table 3.5  Summary of submission status under FEP-02/364/2009

EP Condition

Submission

Date of Submission

Special Conditions, Clause 2.7 & 2.8

Works Schedule and Location Plan

18 May 2011

Special Conditions, Clause 2.6

Environmental Management Organization Chart

18 May 2011

Special Conditions, Clause 2.6

Commencement Date of Works

25 Jun 2011

Special Conditions, Clause 2.9

Noise Management Plan

10 Jun 2011

 

Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

3.1.7.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.6 and Table 3.7.

Table 3.6  Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

N/A

Valid

FEP-01/364/2009

24 Mar 2010

N/A

Valid

Notification of Works Under APCO

313962

2 Feb 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RE0710-11

30 Sept 2011

1 Nov 2011 to 30 Apr 2012

Expired

 

GW-RS0930-11

11 Oct 2011

1 Nov 2011 to 30 Apr 2012

Expired

 

GW-RS0941-11

20 Oct 2011

23 Nov 2011 to 22 May 2012

Expired on 22 May 12

 

GW-RS0955-11

14 Oct 2011

23 Nov 2011 to 22 May 2012

Expired on 22 May 12

 

GW-RS0968-11

20 Oct 2011

18 Nov 2011 to 17 May 2012

Expired on 17 May 12

 

GW-RS1028-11

3 Nov 2011

7 Dec 2011 to 6 June 2012

Valid

 

GW-RS1052-11

18 Nov 2011

21 Nov 2011 to 18 May 2012

Expired on 18 May 12

 

GW-RS1111-11

28 Nov 2011

29 Nov 2011 to 28 May 2012

Valid (Expired on 28 May 2012)

 

GW-RS1116-11

28 Nov 2011

13 Dec 2011 to 12 June 2012

Valid

 

GW-RS1209-11

3 Jan 2012

17 Jan 2012 to 16 July 2012

Valid

 

GW-RS0037-12

19 Jan 2012

1 Feb 2012 to 31 July 2012

Valid

 

GW-RS0051-12

19 Jan 2012

1 Feb 2012 to 31 July 2012

Valid

 

GW-RS0052-12

19 Jan 2012

1 Feb 2012 to 30 April 2012

Expired

 

GW-RS0086-12

30 Jan 2012

3 Feb 2012 to 2 Aug 2012

Cancelled

 

GW-RS0105-12

3 Feb 2012

10 Feb 2012 to 9 Aug 2012

Valid

 

GW-RS0153-12

17 Feb 2012

21 Feb 2012 to 20 Aug 2012

Valid

 

GW-RS0233-12

6 Mar 2012

9 Mar 2012 to 8 Sept 2012

Cancelled

 

GW-RS0255-12

14 Mar 2012

17 Mar 2012 to 15 Sept 2012

Valid

 

GW-RE0283-12

5 Apr 2012

1 May 2012 to

30 Nov 2012

Valid

 

GW-RS0298-12

22 Mar 2012

26 Mar 2012 to 25 June 2012

Valid

 

GW-RS0301-12

20 Mar 2012

21 Mar 2012 to 20 Sept 2012

Valid

 

GW-RS0303-12

26 Mar 2012

27 Mar 2012 to 27 Sept 2012

Valid

 

GW-RS0341-12

3 Apr 2012

28 Apr 2012 to 27 Oct 2012

Valid

 

GW-RS0348-12

3 Apr 2012

10 Apr 2012 to 9 Oct 2012

Valid

 

GW-RS0380-12

12 Apr 2012

1 May 2012 to 31 Oct 2012

Valid

 

GW-RS0388-12

13 Apr 2012

1 May 2012 to 31 Oct 2012

Valid

 

GW-RS0418-12

30 Apr 2012

23 May 2012 to 22 Nov 2012

Valid

 

GW-RS0420-12

30 Apr 2012

18 May 2012 to 17 Nov 2012

Valid

 

GW-RS0423-12

30 Apr 2012

19 May 2012 to 18 Nov 2012

Valid

 

GW-RS0427-12

30 Apr 2012

23 May 2012 to 22 Nov 2012

Valid

 

GW-RS0445-12

30 Apr 2012

1 May 2012 to 25 Sept 2012

Valid

 

GW-RS0467-12

10 May 2012

14 May 2012 to 10 Nov 2012

Valid

 

GW-RS0533-12

21 May 2012

21 May 2012 to 10 Nov 2012

Valid

Construction Noise Permit (CNP) for piling equipment

PP-RS0007-12

27 Mar 2012

28 Mar 2012 to 27 Sept 2012

Valid

Discharge Licence

WT00006249-2010

22 Mar 2010

31 Mar 2015

Valid

 

WT00006436-2010

15 Apr 2010

30 Apr 2015

Valid

 

WT00006673-2010

14 May 2010

31 Mar 2015

Valid

 

WT00006757-2010

28 May 2010

31 May 2015

Valid

 

WT00007129-2010

28 July 2010

31 Jul 2015

Valid

 

WT00008982-2011

26 April 2011

30 April 2016

Valid

 

WT00009691-2011

1 Aug 2011

31 July 2016

Valid

Billing Account under Waste Disposal Ordinance (Land)

7010255

10 Feb 2010

N/A

Valid

Registration as Chemical Waste Producer (Wan Chai)

WPN5213-135-C3593-01

10 Mar 2010

N/A

Valid

Registration as Chemical Waste Producer (TKO 137)

WPN5213-839-C3593-02

22 Sep 2010

N/A

Valid

 

Table 3.7  Summary of submission status under FEP-01/364/2009

EP Condition

Submission

Date of Submission

Special Conditions, Clause 2.7 & 2.8

Works Schedule and Location Plan

14 Jun 2011

Special Conditions, Clause 2.6

Environmental Management Organization Chart

14 Jun 2011

Special Conditions, Clause 2.6

Commencement Date of Works

21 Jun 2011

Special Conditions, Clause 2.9

Noise Management Plan (Revision A)

13 Jan 2012

Condition 2.11

Landscape Plan (Revision B)

21 Feb 2012

Condition 2.9

Noise Management Plan (Rev.A)

13 Jan 2012

 

Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

 

3.1.8.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.8 and Table 3.9.

Table 3.8  Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/18

Permit / Licence / Notification / Approval

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Permit issued

Valid

Notification of Works Under APCO

322293

07 Oct 2010

Notified

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0261-12

09 Mar 2012

10 Mar 2012  br> 09 Sep 2012

Valid

Discharge Licence

WT00008229-2011

13 Jan 2011

31 Jan 2016

Valid

WT00012998-2012

25 May 2012

31 Jan 2016

Valid

Registration as a Waste Producer

WPN: 8335-121-L1048-04

17 Dec 2010

N/A

Registration completed

Billing Account under Waste Disposal Ordinance (Land)

Account No.: 7011587

11 Oct 2010

Account approved

Valid

 

Table 3.9  Summary of submission status under FEP-05/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan

01 March 2011

Condition 2.10

Landscape Plan (Rev. 5)

12 March 2012

 

Contract no. HY/2009/15   Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

3.1.9.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.10 and Table 3.11

 


Table 3.10 Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

N/A

Valid

FEP-06/364/2009/A

22 Nov 2010

N/A

Valid

Notification of Works Under APCO

321822

24 Sep 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS1021-11

4 Nov 2011

10 Nov 2011 to

9 May 2012

Cancelled

 

GW-RS1211-11

22 Dec 2011

24 Dec 2011 to

21 Jun 2012

Valid

 

GW-RS1149-11

7 Dec 2011

8 Dec 2011 to

7 Jun 2012

Cancelled

 

GW-RS1138-11

7 Dec 2011

8 Dec 2011 to

21 May 2012

Cancelled

 

GW-RS0997-11

2 Nov 2011

2 Nov 2011 to

2 May 2012

Expired on 5 May 2012

 

GW-RS1021-11

4 Nov 2011

10 Nov 2011 to

9 May 2012

Cancelled

 

GW-RS0150-12

22 Feb 2012

27 Feb 2012 to

24 Aug 2012

Cancelled

 

GW-RS0094-12

1 Feb 2012

3 Feb 2012 to

31 Jul 2012

Valid

 

GW-RS0330-12

29 Mar 2012

3 Apr 2012 to

21 Sep 2012

Valid

 

GW-RS0328-12

30 Mar 2012

1 Apr 2012 to

22 Sep 2012

Valid

 

GW-RS0190-12

28 Feb 2012

28 Feb 2012 to

11 Aug 2012

Cancelled

 

GW-RS0249-12

10 Feb 2012

9 Mar 2012 to

31 Aug 2012

Valid

 

GW-RS0552-12

24 May 2012

25 May 2012 to

20 Oct 2012

Valid

Registration as a Chemical Waste Producer

WPN: 5213-147-C1169-35

15 Nov 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7011553

30 Sep 2010

27 Sep 2010 to

27 Jan 2016

Valid

Water Discharge License (Discharge at TS1)

WT00008780-2011

24 Nov 2011

24 Nov 2011 to 31 Mar 2016

Valid

Water Discharge License (Discharge at Hung Hing Road)

WT00010482-2011

30 Sep 2011

30 Sep 2011 to 30 Sep 2013

Cancelled

Water Discharge License (Discharge at CHT area)

WT00012941-2012

10 May 2012

10 May 2012 to 31 May 2014

Valid

Water Discharge License (Discharge at  TPCWAE)

WT00011322-2011

15 Dec 2011

15 Dec 2011 to 31 Dec 2013

Valid

Water Discharge License (Discharge at TS4)

WT00011718-2012

16 Jan 2012

16 Jan 2012 to 31 Jan 2014

Valid

Table 3.11 Summary of submission status under FEP-06/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

11 Mar 2011

Amendment for Management Organization of Main Construction Companies

16 May 2011

Condition 2.7

Works Schedule

15 Mar 2011

Condition 2.8

Location Plan

15 Mar 2011

Condition 2.23

Noise Management Plan

6 May 2011

 

Contract no. HY/2009/19  Central   Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

3.1.10.    The current status on licences and/or permits on environmental protection pertinent and submission under FEP-07/364/2009/A for contract no. HY/2009/19 are shown in Table 3.12 and Table 3.13.

Table 3.12 Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/19

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

N/A

Valid

Notification of Works Under APCO

326160

24 Jan 2011

N/A

Valid

Registration as a Waste Producer

7012306

10 Feb 2011

N/A

Valid

Registration as Chemical Waste Producer

5213-151-C3654-01

24 Mar 2011

N/A

Valid

Application for Vessel Disposal

7012306

21 July 2011

N/A

Valid

Construction Noise Permit (CNP)

GW-RS1097-11

22-Nov-11

07-May-12

Cancelled

 

GW-RS0180-12

22-Feb-12

(Effective 27-Feb-12)

26-Aug-12

Valid

 

GW-RS0507-12

22-May-12

(Effective 24-May-12)

23-Nov-12

Valid

 

GW-RS0028-12

18-Jan-12

17-Jun-12

Valid

 

GW-RS0286-12

23-Mar-12

(Effective 27-Mar-12)

26-Sep-12

Cancelled

Water Discharge Licence

WT00010093-2011

31-Aug-11

30-Sep-16

Valid

 

WT00010865-2011

3-Nov-11

30-Nov-16

Valid

 

Table 3.13 Summary of submission status under FEP-07/364/2009/A

EP Condition

Submission

Date of Submission

Condition 2.9

Noise Management Plan

02 Jun 2011

Condition 2.13

Landscape Plan

16 March 2012

Condition 2.9

Noise Management Plan(Rev.2)

28-Oct-11

4     Monitoring Requirements

4.1               Noise Monitoring

Noise Monitoring Stations

4.1.1.        The noise monitoring stations for the Project are listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.1  Noise Monitoring Stations

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

 

Real time Noise Monitoring Stations

4.1.2.        Review of feasibility on the real time noise monitoring stations was conducted in July with IEC. Station, RTN1a, Tung Lo Wan fireboat Station was found not appropriate to be a monitoring station for monitoring the IECL Piling works and Demolition after visited. 

4.1.3.        The noise monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.2  Real Time Noise Monitoring Stations

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitefield Depot

North Point

RTN2

Oil Street Community Liaison Centre

 

Noise Monitoring Parameters, Frequency and Duration

4.1.4.        The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

4.1.5.        Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

 -           One set of measurements between 0700 and 1900 hours on normal weekdays.

4.1.6.        Real time noise shall be carried out at the designated monitoring stations. The following is an initial guide on the regular monitoring frequency for each station on a 24 hours daily basis when noise generating activities are underway:

 -           One set of measurements between 0700 and 1900 hours on normal weekdays.

 -           One set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.

 -           One set of measurements between 2300 and 0700 hours on next day on everyday.

4.1.7.        If construction works are extended to include works during the hours of 1900  0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

Monitoring Equipment

4.1.8.        As referred to in the Technical Memorandum  issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.1.9.        Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

4.1.10.    The sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency before deployment to the site and during each site visit. Measurements will be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.2               Air Monitoring

Air Quality Monitoring Stations

4.2.1.        The air monitoring stations for the Project are listed and shown in Table 4.3 and Figure 4.1.. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.


Table 4.3  Air Monitoring Stations

Station ID

Monitoring Location

Description

CMA1b

Oil Street Community Liaison Centre

North Point (Re-commenced on 14 November 2011)

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office *

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5a

Children Garden opposite to Pedestrian Plaza

Wan Chai

MA1e

International Finance Centre (Eastern End of Podium)

Central

MA1w

International Finance Centre (western End of Podium)

Central

Remarks: As per the ENPC meeting in March 2011, the monitoring stations CMA3a  Future CWB site office at Wanchai Waterfront Promenade was renamed as remark.

 

Air Monitoring Parameters, Frequency and Duration

4.2.2.        One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

4.2.3.        All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

4.2.4.        For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

4.2.5.        High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

 -           0.6  1.7 m3 per minute adjustable flow range;

 -           Equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

 -           Installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

 -           Capable of providing a minimum exposed area of 406 cm2;

 -           Flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

 -           Equipped with a shelter to protect the filter and sampler;

 -           Incorporated with an electronic mass flow rate controller or other equivalent devices;

 -           Equipped with a flow recorder for continuous monitoring;

 -           Provided with a peaked roof inlet;

 -           Incorporated with a manometer;

 -           Able to hold and seal the filter paper to the sampler housing at horizontal position;

 -           Easily changeable filter; and

 -           Capable of operating continuously for a 24-hour period.

 

4.2.6.        Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

Laboratory Measurement / Analysis

4.2.7.        A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

4.2.8.        Filter paper of size 8 x 10  shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

4.2.9.        After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

4.2.10.    All the collected samples shall be kept in a good condition for 6 months before disposal.

4.2.11.    Current calibration certificates of equipments are presented in Appendix 4.2.

5.0    Monitoring Results

5.0.1.        The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1. The monitoring results are presented in according to the Individual Contract(s).

5.0.2.        In the reporting month, the concurrent contracts are as follows:

Ÿ         Contract no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

Ÿ         Contract no. HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009

Ÿ         Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

Ÿ         Contract no. HY/2009/19  Central   Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009

Ÿ         Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention and Exhibition Centre

Ÿ         Contract no. HK/2009/02 Wan Chai Development Phase II  Central-Wan Chai Bypass at Wan Chai East

5.0.3.        The environment monitoring schedules for reporting month and coming month are presented in Appendix 5.1.

5.1               Noise Monitoring Results

5.1.1.        Monitoring for report of review baseline noise level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20 June 2011, verified by IEC on 18 July 2011 and was approved by ER by January 2012. The new baseline is used for the noise calculation of this reporting month starting from January 2012.

5.1.2.        Due to adverse weather condition, the noise monitoring at the following stations were rescheduled

M7e: from 16 May 2012 to 18 May 2012

M7w: from 16 May 2012 to 18 May 2012


Contract no. HY/2009/17 –Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009

5.1.3.        The proposed division of noise monitoring stations for Contract no. HY/2009/17 are summarized in Table 5.1 below:

Table 5.1   Noise Monitoring Stations for Contract no.  /span>HY/2009/17

Station

Description

M4b

Victoria Centre

 

5.1.4.        No action or limit level exceedance was recorded during daytime period in the reporting month. Noise monitoring results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2. 

Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

5.1.5.        Noise monitoring for the Central Interchange works under contract no. HY/2009/18 was commenced on 22 April 2011.The proposed division of noise monitoring stations for Contract no. HY/2009/18 are summarized in Table 5.2 below:

Table 5.2   Noise Monitoring Stations for Contract no. HY/2009/18

Station

Description

M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

 

5.1.6.        No action level exceedance and one limit level exceedance was recorded during daytime period in the reporting month.

5.1.7.        During 30 April 2012 monitoring, a limit level exceedance was recorded at M7e  International Finance Centre (Eastern End of Podium). After checking with contractor’s work schedules and investigation found that backhoe with breaker and excavator for diaphragm wall construction were conducted during monitoring. 

5.1.8.        The limit level exceedance was considered as project-related.

5.1.9.        Noise monitoring results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02  Wan Chai Development Phase II   Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.1.10.    The commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of noise monitoring stations are summarized in Table 5.3 below.

Table 5.3   Noise Monitoring Station for Contract no HK/2009/01 and HK/2009/02

Station

Description

M1a

Harbour Road Sports Centre

 

5.1.11.    No action or limit level exceedance was recorded in the reporting month. Noise monitoring results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2. 

Contract no. HY/2009/15  Central-Wanchai Bypass   Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

5.1.12.    The commencement of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Noise monitoring was commenced on 13 July 2011. The proposed divisions of noise monitoring stations are summarized in Table 5.4 below.

 

Table 5.4   Noise Monitoring Stations for Contract no. HY/2009/15

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

5.1.13.    No action or limit level exceedance was recorded in this reporting month.

5.1.14.    Noise monitoring results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

Contract no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

 

5.1.15.    Noise monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The proposed division of noise monitoring stations are summarized in Table 5.5 below.

Table 5.5   Noise Monitoring Stations for Contract no. HY/2009/19

Station

Description

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

5.1.16.    No action level and two limit level exceedances were recorded on 30 April and 16 May 2012 at M6  HK Baptist Church Henrietta Secondary School in the reporting month.

5.1.17.    Major traffic jam and no major work activities were observed during monitoring, the exceedances were considered as non-project related.

5.1.18.    Noise monitoring results measured in this reporting period are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2. Details of the Notification of Exceedance can be referred in Appendix 6.2.

5.2               Real Time Noise Monitoring Results

5.2.1.        No construction activity was conducted during nighttime period (2300 to 0700) in this reporting month.

Contract no. HY/2009/17 –Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009 and Contract no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

5.2.2.        The proposed division of noise monitoring stations are summarized in Table 5.6 below. Real time noise monitoring for the piling works under contract no. HY/2009/17 was commenced on 5 October 2010

Table 5.6  Real Time Noise Monitoring Stations for Contract no. HY/2009/17

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitefield Depot

Real time noise monitoring results and graphical presentation during night time period are for information only.

5.2.3.        No action and limit level exceedance were recorded in the reporting period. Real time noise monitoring results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 5.4 .

5.2.4.        The proposed division of noise monitoring stations are summarized in Table 5.7 below. Real time noise monitoring for major construction works under contract no. HY/2009/19 was commenced on 24 April 2011.

Table 5.7  Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitefield Depot

RTN2

North Point

Oil Street Community Liaison Center

Real time noise monitoring results and graphical presentation during night time period are for information only.

5.2.5.        No action and limit level exceedance were recorded in the reporting period. Real time noise monitoring results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 5.4 .

5.3               Air Monitoring Results

5.3.1          Due to extension of site boundary by contractor of HY/2009/19, location of air monitoring station CMA1b  Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.

5.3.2          Due to lack of electricity supply, the 24-hr TSP monitoring at the following stations were rescheduled:

CMA1b: from 8 May 2012 to 9 May 2012

CMA5a: from 8 and 25 May 2012 to 9 and 26 May 2012

MA1e: from 14 May 2012 to 15 May 2012

 

5.3.3          The data for the rescheduled air monitoring for CMA1b, dated 30 April 2012, will be presented in the next monthly report (May 2012).

Contract no. HY/2009/17 –Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009

5.3.4          The proposed division of air monitoring stations are summarized in Table 5.8 below. Air monitoring for the piling works under contract no. HY/2009/17 was commenced on 8 October 2010.

Table 5.8   Air Monitoring Station for Contract no. HY/2009/17

Station

Description

CMA1b

Oil Street Community Liaison Centre

CMA2a

Causeway Bay Community Centre

5.3.5          No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

5.3.6          Air monitoring for the Central Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011.The proposed division of air monitoring stations are summarized in Table 5.9 below.

Table 5.9   Air Monitoring Stations for Contract no. HY/2009/18

Station

Description

MA1e

International Finance Centre (Eastern End of Podium)

MA1w

International Finance Centre (Western End of Podium)

 

5.3.7          No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009

5.3.8          The commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality monitoring was commenced on 25 August 2011. The proposed division of air monitoring stations are summarized in Table 5.10 below.

Table 5.10 Air Monitoring Station for Contract no. HK/2009/01

Station

Description

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

5.3.9          No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.3.10      The commencement of construction works for HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of air monitoring stations are summarized in Table 5.11 below.

Table 5.11 Air Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

5.3.11      No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

Contract no. HY/2009/15  Central-Wanchai Bypass   Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

5.3.12      The commencement of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air quality monitoring was commenced on 14 July 2011. The proposed division of air monitoring stations are summarized in Table 5.12 below.

Table 5.12 Air Monitoring Station for Contract no. HY/2009/15

Station

Description

CMA3a

CWB PRE Site Office

5.3.13      No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3. 

 

Contract no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

5.3.14      The proposed division of air monitoring stations are summarized in Table 5.13 below. Air monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 26 April 2011.

Table 5.13 Air Monitoring Stations for Contract no. HY/2009/19

Station

Description

CMA1b

Oil St Community Liaison Centre

CMA2a

Causeway Bay Community Centre

5.3.15      No exceedance was recorded in the reporting month. Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air monitoring results and graphical presentation can be referred in Appendix 5.3.


Waste Monitoring Results

Contract no. HY/2009/17 –Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009

5.4.1.        No Inert and non-inert C&D wastes were disposed in the reporting month. Details of the waste flow table are summarized in Table 5.14

Table 5.14 Details of Waste Disposal for Contract no. HY/2009/17

Waste Type

Quantity this month, m3

Cumulative Quantity-to-Date, m3

Disposal / Dumping Grounds

Inert C&D materials disposed

NIL

NIL

N/A

Inert C&D materials recycled

NIL

1354.82

N/A

Non-inert C&D materials disposed

NIL

NIL

N/A

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

N/A

N/A

N/A

 

Contract nos. HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009

5.4.2.        Inert and non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.15.

Table 5.15 Details of Waste Disposal for Contract no. HK/2009/01

Waste Type

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

474.83

19,171.45

TKO137, TM38

Inert C&D materials recycled

NIL

389.96

N/A

Non-inert C&D materials disposed

54.16

710.92

SENT Landfill

Non-inert C&D materials recycled

570

136,324

N/A

Chemical waste disposed

370

6,130

N/A

 


 

Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

5.4.3.        Inert C&D & non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.16.

Table 5.16 Details of Waste Disposal for Contract no. HK/2009/02

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

17,179

140,130

TKO137, TM 38

Inert C&D materials recycled

NIL

NIL

N/A

Non-inert C&D materials disposed

35

284

SENT Landfill

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed (kg)

NIL

4,186

N/A

Remarks Contractor clarified and updated waste flow table for the reporting month of April

Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

 

5.4.4.        Inert C&D and non-inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.17.

Table 5.17 Details of Waste Disposal for Contract no. HY/2009/18

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

10,941.9

31,935

T.K.O. 137, TM 38

Inert C&D materials recycled

3,461.5

7,963

N/A

Non-inert C&D materials disposed

51.6

311

SENT Landfill

Non-inert C&D materials recycled (tonnes)

NIL

40.3

N/A

Chemical waste disposed (kg)

1,400

2,225

N/A

Remarks Contractor clarified and updated waste flow table for the reporting month of April


Contract no. HY/2009/15  Central-Wanchai Bypass   Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

5.4.5.        Inert & Non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.18.

Table 5.18 Details of Waste Disposal for Contract no. HY/2009/15

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

72.5

127,804.5

Tuen Mun Area 38

 

31627.2

96,784.5

TKO137 FB

Inert C&D materials recycled

NIL

415.9

HY/2009/11 

ex-PCWA 

TS4

Non-inert C&D materials disposed

59.9

230.7

SENT Landfill

Non-inert C&D materials recycled

5.9

369.9

Xun Xiang Metalware

Skylight Recycle (paper)

Chemical waste disposed

NIL

8000

Dunwell Group

Remarks Contractor clarified and updated waste flow table for the reporting month of January.

 

Contract no. HY/2009/19  Central   Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

5.4.6.        Inert and Non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.19.

Table 5.20 Details of Waste Disposal for Contract no. HY/2009/19

Waste Type*

Quantity this month,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

19122.06

85618.44

N/A

Inert C&D materials recycled

NIL

1801.91

N/A

Non-inert C&D materials disposed

20.48

461.39

SENT Landfill

Non-inert C&D materials recycled

9.08

42.7

N/A

Chemical waste disposed

0.54

4.13

N/A

 /span>Remarks Contractor clarified and updated waste flow table for the reporting month of April

6     Compliance Audit

6.0.1.        The Event Action Plan for construction noise, air qualities are presented in Appendix 6.1.

6.1               Noise Monitoring

 

Contract no. HY/2009/17 –Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009

6.1.1.        No exceednace was recorded in the reporting month.

Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

6.1.2.        No action and one limit level exceedance was recorded at M7e on 30 April 2012 in the reporting month.

6.1.3.        During 30 April 2012 monitoring, a limit level exceedance was recorded.  After checking with contractor’s work schedules and investigation found that backhoe with breaker and excavator for diaphragm wall construction were conducted during monitoring.

6.1.4.        The limit level exceedance was considered as project-related.

Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention Exhibition Centre  Tunnel Works under FEP-02/364/2009

6.1.5.        No exceedance was recorded in the reporting month.

Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

6.1.6.        No exceedance was recorded in the reporting month.

Contract no. HY/2009/15  Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

6.1.7.        No action or limit level exceedance was recorded in the reporting month.

Contract no. HY/2009/19  Central  Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

6.1.8.        No action level and two limit level exceedances were recorded at M6  HK Baptist Church Henrietta Secondary School on 30 April and 16 May 2012 in the reporting month.  /span>Investigation found that major traffic noise was contributed in the noise monitoring and not related to the Project.

Real Time Noise Monitoring

Contract no. HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009

6.1.9.        No exceednace was recorded in the reporting month.

Contract no. HY/2009/19  Central   Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

6.1.10.    No exceednace was recorded in the reporting month.

6.2               Air Monitoring

 

Contract no. HY/2009/17  Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under FEP-03/364/2009

6.2.1.        No exceedance was recorded in the reporting month.

 

Contract no. HY/2009/18  Central  Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A

6.2.2.        No exceednace was recorded in the reporting month.

Contract no. HK/2009/01  Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong Convention and Exhibition Centre  Tunnel Works under FEP-02/364/2009

6.2.3.        No exceednace was recorded in the reporting month.

Contract no. HK/2009/02  Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

6.2.4.        No exceednace was recorded in the reporting month.

Contract no. HY/2009/15  Central-Wanchai Bypass   Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A

6.2.5.        No exceednace was recorded in the reporting month.

Contract no. HY/2009/19  Central   Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

6.2.1          No exceednace was recorded in the reporting month.

6.3               Review of the Reasons for and the Implications of Non-compliance

6.3.1.        There was no non-compliance from the site audits in the reporting period. The observations and recommendations made in each individual site audit session were presented in Section 8.

6.3.2.        No project-related non-compliance from monitoring was recorded in the reporting month.

6.4               Summary of action taken in the event of and follow-up on non-compliance

6.4.1          There was no particular action taken since no project-related non-compliance was recorded from the site audits and environmental monitoring in the reporting period.

6.4.2          There was exceedance of noise level recorded on 30 April 2012 at M7e that was considered in relation to backhoe with breaker and excavator for diaphragm wall construction were conducted during monitoring.


7                     Cumulative Construction Impact due to the Concurrent Projects

7.0.1.        According to Condition 3.4 of the EP-364/2009/A, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai East (CWB Tunnel).

7.0.2.        According to the Monthly EM&A report (April 2012) of Central Reclamation Phase III (CRIII), filling works, building construction works and pipe works were performed in the April 2012 reporting month. The water quality monitoring was completed in October 2011 and no exceedance was recorded for air and noise monitoring. It can be concluded that cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was insignificant.

7.0.3.        According to the construction programme of Central Reclamation Phase III, Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activity under Central Reclamation Phase III were general filling works in IRAE; Wan Chai Development Phase II was marine works at HKCEC areas, cross-harbour Watermains, Fresh Watermains, Cooling Watermains and Salt Watermains Installations, tunnel works at Wan Chai East, diaphragm wall construction at TS4; dredging at TS2; deep excavation at TS1 and TPCWAE TCBR1W. Advanced piling works at FEHD Whitfield Depot, Central Interchange, and diaphragm wall construction at North Point area. The major environmental impact was water quality impact at Causeway Bay and Wan Chai. Land-based construction activity were Diaphragm wall construction at TS4, Diaphragm wall construction at TS1 and TPCWAE TCBR1W, piling works at FEHD Whitfield Depot, Diaphragm wall at Central and North Point and tunnel works at Wan Chai East in the reporting month.

7.0.4.        The major environmental impacts generated from CRIII advanced piling works at FEHD Whitfield Depot were undertaken and Diaphragm wall construction at Central and tunnel works at Wan Chai East, IECL and Causeway Bay typhoon shelter in the reporting month. No significant air impact was anticipated in the reporting month. Notwithstanding, one project-related exceedance regarding construction noise was recorded during non-restricted hours referred to Contract no. HY/2009/18 in the reporting month. In general, it is evaluated that the cumulative construction impact from the concurrent projects including Wan Chai Development Phase II was mainly insignificant.

8     Environmental Site Audit

8.0.1.        During this reporting month, weekly environmental site audits were conducted for Contracts no. HY/2009/15, HY/2009/17, HY/2009/18, HY/2009/19, HK/2009/01 and HK/2009/02. No non-conformance was identified during the site audits.

8.0.2.        Four site inspections for Contract no. HY/2009/15 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.1.

Table 8.1  Summary of Environmental Inspections for Contract no. HY/2009/15

Date

Item

Observations

Action taken by Contractor

Outcome

3-May-12

120503_01

Oil leakage should be cleared as chemical waste (TPCWAE).

Oil leakage was cleared as chemical waste.

Completion as observed on 8-May-12

3-May-12

120503_02

Adequate drip trays should be provided for oil drums.(TPCWAE, TS4, TS1)

Provided drip trays for oil drums.

Completion as observed on 15-May-12

8-May-12

120508_01

Muddy water was observed at discharge point.  Actions should be taken to prevent muddy water leaking into sea. (breakwater of TPCWAE)

Area around discharge point was cleared of mud.

Completion as observed on 15-May-12

8-May-12

120508_02

Blockage at public manholes should be cleared (Gate of TS4, outside POC)

Removal of mud inside manholes.

Completion as observed on 15-May-12

8-May-12

120508_03

Adequate drip trays should be provided for oil drums/drums.

Drip trays were provided for oil drums/drums.

Completion as observed on 15-May-12

15-May-12

120515_01

Oil leakage and stains should be cleared as chemical waste. (Gate of TS4, POC, TPCWAE)

Oil leakage was cleared as chemical waste.

Completion as observed on 25-May-12

15-May-12

120515_02

U-channels should be cleared of blockage (TS1, TPCWAE).

Blockage at u-channels was cleared.

Completion as observed on 25-May-12

15-May-12

120515_03

Adequate drip trays should be provided for oil drums/drums. (TS1, TPCWAE)

Drip trays were provided for oil drums/drums.

Completion as observed on 25-May-12

15-May-12

120515_04

Better protection around manholes should be provided to avoid runoff into public drainage system before treatment. (outside gate of TS4)

Sandbags were provided around the public gullies and better wheel-wash practice was adopted.

Completion as observed on 25-May-12

 

8.0.3.        Four site inspections for Contract no. HY/2009/18 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.2.


Table 8.2  Summary of Environmental Inspections for Contract no. HY/2009/18

 

Item

Date

Observations

Action taken by Contractor

Outcome

120503_01

3-May-12

Noise blankets should be erected when performing noisy operations.

Noise blankets were erected during construction.

Completion as observed on 10-May-12

120524_01

24-May-12

Adequate drip tray should be provided for oil drums (Near Gate 2)

Oil drums were removed.

Completion as observed on 31-May-12

120524_02

24-May-12

Noise blankets and barriers should be deployed during noisy activities (Deep excavation area)

Erection of noise blankets and deployment of movable noise barriers.

Completion as observed on 31-May-12

8.0.4.         Four site inspections for Contract no. HY/2009/19 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.3.

Table 8.3  Summary of Environmental Inspections for Contract no. HY/2009/19

Item

Date

Observations

Action taken by Contractor

Outcome

120502_01

2-May-12

Gaps and holes on platforms should be covered or filled to avoide runoff into sea.

Covered gaps and holes with tarpaulin sheet on platforms.

Partial Completion observed on 9-May-12

120509_01

9-May-12

Blockage at U-channel should be cleared to avoid runoff out of site area (Near Oil Street).

Cleared mud from U-channel.

Completion as observed on 16-May-12.

120516_01

16-May-12

Noise blankets should be erected during noisy operations (platform 5).

Noise blankets were provided at working platforms.

Completion as observed on 30-May-12

120516_02

16-May-12

Muddy trail should be cleared and avoided out of site area (outside gate at Oil Street).

Cleared muddy trail ouside gate of Oil Street.

Completion as observed on 23-May-12

120523_01

23-May-12

Muddy water was observed washed into public gully without treatment, please make sure steps should be taken to prevent further runoff. (Gate at Watson Road)

Muddy water was cleared.

Completion as observed on 30-May-12

120523_02

23-May-12

Although the contractor has immediately performed remedial measures after bursting of bentonite pipe, steps should be taken to prevent runoff out of site area and all muddy water that got out should be cleared (U-channel near Oil Street)

Muddy water was cleared and sandbags were provided around the u-channel.

Completion as observed on 30-May-12

120523_03

23-May-12

Grouting machine at portion III should be covered properly to avoid cement coming out of mixing area (portion III)

Extra tarpaulin was placed on all sides of grouting area.

Completion as observed on 30-May-12

8.0.5.        Four site inspections for Contract no. HK/2009/01 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.4.

Table 8.4  Summary of Environmental Inspections for Contract no. HK/2009/01

Item

Date

Observations

Action taken by Contractor

Outcome

120502_01

2-May-12

The direct discharge was observed in the pumping station that the discharge should not be allowed and it should be treated by sedimentation tank or geo-textile before discharge

The pipe for discharge was removed from sea.

Completion as observed on 9-May-12.

120509_01

9-May-12

The exposed soil area around tree (A160) should be surrounded by sandbags (Renaissance Harbour View Hotel)

Exposed soil area around tree (A160) was surrounded by sandbags

Completion as observed on 17-May-12.

120509_02

9-May-12

The muddy water from wheel washing facilities was observed on the roadside which should be cleaned regularly and the spillage of muddy water should be prevented. (Water Channel)

Muddy water from wheel wash was cleared from public road.

Completion as observed on 17-May-12.

120509_03

9-May-12

The cement bags should be covered by tarpaulin sheet completely (Water Channel)

Cement bags were covered.

Completion as observed on 17-May-12.

120517_01

17-May-12

Drip tray should be provided for oil drums (Water Channel, Renaissance View Hotel workfront)

Drip tray was provided for oil drums.

Completion as observed on 23-May-12.

120523_01

23-May-12

The muddy water was observed near to the roadside which should be cleaned (Expo Drive West)

Muddy water was cleared from road.

Completion as observed on 30-May-12.

120523_02

23-May-12

The silt was observed on the public area which should be cleaned (VIP area)

Silt was removed from public area.

Completion as observed on 30-May-12.

 

8.0.6.        Four site inspections for Contract no. HK/2009/02 was carried out during this reporting period. The results of these inspections and outcomes are summarized in Table 8.5.


Table 8.5   Summary of Environmental Inspections for Contract no. HK/2009/02

Item

Date

Observations

Action taken by Contractor

Outcome

120503_01

3-May-12

The stagnant pool of water was observed in the U-channel, which should be cleaned regularly to prevent overflow (WCRI)

Stagnant water was removed.

Completion as observed on 10-May-12

120510_01

10-May-12

The cement mixing plants should be covered by three sides enclosure. (WSD pumping station, WCRI)

Three side enclosure was provided for cement mixing plants.

Completion as observed on 16-May-12

120510_02

10-May-12

The bentonite bags should be covered by tarpaulin sheet (WCR1)

Bentonite bags were covered by tarpaulin sheet.

Completion as observed on 16-May-12

120510_03

10-May-12

Due to the hot weather, the site area should be sprayed by water regularly for dust suppression.

Water spraying was performed for dust suppression.

Completion as observed on 16-May-12

120510_04

10-May-12

The direct discharge of muddy water from WCRI was observed

Discharge was treated prior to be discharged.

Completion as observed on 16-May-12

120516_01

16-May-12

Drip tray was not provided for oil drum (WCR 1)

Drip trays were provided for the oil drum,

Completion as observed on 24-May-12

120516_01

16-May-12

The silt deposited on U-channel should be cleaned regularly to prevent overflow of muddy runoff (Hung Hing Road)

Silt at u-channel was cleared.

Completion as observed on 24-May-12

120524_01

24-May-12

The stagnant water accumulated inside the drip tray was observed (WCR1)

Stagnant water inside trip tray was cleared.

Completion as observed on 31-May-12

120524_02

24-May-12

The discharge of water to the pedestrian way was observed. (Harbour Road)

The pipe of discharge was removed.

Completion as observed on 31-May-12

120524_03

24-May-12

The stockpile was not covered by tarpaulin sheet. (Harbour Road)

The stockpile was covered by tarpaulin.

Completion as observed on 31-May-12

8.0.7.        Four site inspections for Contract no. HY/2009/17 were carried out during this reporting period. No observation was found in the reporting month.

9     Complaints, Notification of Summons and Prosecution

9.0.1.        No environmental complaint was received in the reporting period.

9.0.2.        The details of cumulative complaint log and updated summary of complaints are presented in Appendix 9.1

9.0.3.        Cumulative statistic on complaints and successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.

Table 9.1  Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

May 12

0

Sep 10 to Apr 12

20

Total

20

 

Table 9.2  Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Total

-

0

0

10.    Conclusion

10.0.1.    The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

10.0.2.    The scheduled construction activities and the recommended mitigation measures for the coming month are listed in Table 10.1. The construction programmes of individual contracts are provided in Appendix 10.1.

Table 10.1   Summary of Key Construction Activities of Individual Contract(s) to be commenced in Coming Reporting Month

Contract No.

Key Construction Works

Recommended Mitigation Measures

HY/2009/15

 -          Diaphragm wall construction works at TS4

 -          Cut and Cover Tunnel Construction at TPCWAE

 -          Night time protection works at CHT

 -          Cut off wall preparation works at Hung Hing Road and POC

 -          Watering any dust generating activities

 -          Checking all drip trays frequently and clear any stagnant water and mud inside it.

 -          Noise control measures shall be provided during restricted hours.

 

HY/2009/17

 -          ELS works for basement construction for pile cap construction.

 -          Noise barrier shall be implemented; and

 -          Watering any dust generating activities

HY/2009/18

 -          Trial pit

 -          Instrumentation and monitoring works

 -          Drainage works

 -          Site investigation and pre-drilling works

 -          D-wall construction

 -          Sheet piling

 -          Grout curtain

 -          Tree Transplantation

 -          Earthworks

 -          Preparation works in existing tunnel

 -          Stitch coring

 -          Approach ramp structure works

 -          Top down slab

 -          Road works

 -          Tunnel works

 -          Excavation and Lateral Support

 -          Noise barrier shall be implemented; and

 -          Noise level shall be controlled by reducing piling rate and no. of plants working in parallel.

 -           Dust control during dust generating works

 -           Provide protection works to ensure no runoff out of site area or direct discharge into public drainage system.

HY2009/19

 -          Road works at Watson Road

 -          Fabrication of bored piling platform

 -          Bored piling (Land)

 -          Ground contamination assessment

 -          Pre-drilling works for bored pile and Diaphragm wall

 -          D-wall Construction (North & South Section)

 -          Guide wall construction for D-wall / Barette at North side

 -          Construction works for Box Culvert T

 -          Marine Piling

 -          Construct ion of socket-H pile for Marine works

 -          Construction of pre-bored H-pile works for Culvert U

 -          Construction of 1500 drainage along D-wall

 -          Construction of sheet pile at D9 location.

 -           Noise level shall be controlled by reducing the pilling operation rate.

 -           Noise barrier shall be implemented.

 -           Dust control during dust generating works

 -           Provide protection works and adequate drainage system to ensure no direct discharge into public drainage system or the sea.

HK2009/01

 -          Diaphragm wall construction for CWB tunneling works at Stage2

 -           /span>Piling works for SCL Protection Works

 -           /span>Installation of dewatering system for construction of CWB tunnel, SCL top slab and Exhaust duct at Stage 1

 -           /span>Construction of CWB top slab would be continued

 -           /span>Construction of SCL top slab and exhaust duct at Stage 1

 -            /span>Pipe bridge erection upon completion of pipe laying works across exhaust duct, bulk excavation for construction of exhaust duct structure after installation of pipe bridge

 -          Noise level shall be controlled by reducing pilling rate and no. of plants working in parallel.

 -          Well maintain the enclosures for grouting and bentonite mixing plants.

 -          Provide protection works and adequate drainage system to ensure no direct discharge into public drainage system or the sea.

 

HK/2009/02

 -          Deep excavation works below -8.8mPD for western tunnel portion and below +5.8mPD for eastern tunnel portion.

 -           Drilling bored pile to rock head, breaking concrete slab and excavation of trial pit at tunnel portion 3 & 4.

 -           Well maintain the enclosures for grouting and bentonite mixing plants.

 -           Dust control during dust generating works

 -           Provide protection works to ensure no runoff out of site area or direct discharge into public drainage system.

 

10.0.3.    The construction works of Contract no. 04/HY/2006  Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by the Contractor on 11 February 2011.